Kruger's flood repairs will cost R950m, and R481m is still missing
Repairing Kruger National Park after January's floods will cost R949.9 million, but SANParks is R481.2 million short and has spent only R86.8 million so far. Here's where the money goes and what it means for your visit.

Fixing the damage January's floods did to the Kruger National Park will cost R949.9 million (excluding VAT), and SANParks is still R481.2 million short. By 30 September only R86.8 million had been spent. That's according to the environment minister's written reply to Parliament (PMG).
Most of the money that's missing is for gravel and management roads, which insurance doesn't cover (PMG).
Where is the R950 million going?
| Item | Estimated cost (excl. VAT) |
|---|---|
| All roads | R640.2 million |
| Bridges and culverts | R196.3 million |
| Buildings, fences and civil works | R113.4 million |
| Total | R949.9 million |
Source: Minister's reply, PMG
Who is paying for it?
| Funding | Amount (excl. VAT) |
|---|---|
| Government (environment department) | R218.3 million |
| Insurance settlement | R149.5 million |
| SANParks' own money | R100 million |
| Kruger Recovery Fund | R0.9 million |
| Total received | R468.6 million |
| Still missing | R481.2 million |
Source: Minister's reply, PMG
So far 23 repair projects worth R188.3 million have been contracted, and 10 more bridge, drainage and drift projects (about R57.3 million) are still being designed (PMG).
What happened in January?
Heavy rain between 10 and 20 January washed away roads and damaged bridges, camps and water infrastructure (SAnews). Letaba Rest Camp was among the worst hit (SANParks).
Visitor numbers dipped: about 90,000 people visited in February, 7,000 fewer than a year earlier (Daily Investor, via Bloomberg).
Is Kruger open, and what does this mean for my trip?
Yes, the park is open and people are driving the rebuilt roads. Minister David Maynier said the second phase of repairs will be done before peak season towards the end of November 2026 (SAnews).
Full recovery will take much longer. SANParks CEO Hapiloe Sello said it could take "perhaps five years" at the current pace to get all infrastructure back to working condition (SAnews).
Some roads and gates may still be closed or detoured. Skukuza's main gate, for example, is closed from 2 November to 4 December 2026 with a temporary entrance in use (Reported). Check SANParks' official site or call the park before you go.
Are they just patching the old roads?
No. SANParks says it's rebuilding roads, bridges, culverts and drainage to cope better with future floods, using a climate risk study that was already under way before January (PMG).
FAQ
How much will Kruger's flood repairs cost?
R949.9 million excluding VAT, according to the minister's reply to Parliament.
How big is the funding gap?
R481.2 million, mainly for gravel and management roads that insurance doesn't cover.
Is Kruger National Park open?
Yes. Phase two of repairs is due before peak season at the end of November 2026, but check SANParks for road and gate closures before you travel.